(영문) 대구지방법원포항지원 2015.09.11 2014가합40034

채무부존재확인

Text

1. The separate list based on the purchase agreement dated June 17, 2013 between the Plaintiff (Counterclaim Defendant) and the Defendant (Counterclaim Plaintiff) is written.

Reasons

1. Facts of recognition;

A. 1) The Plaintiff is a corporation running the design and manufacturing business of industrial machinery, the manufacturing business of steel structures, etc., and Posco Construction Co., Ltd. (hereinafter “Posco Construction”).

(2) The Defendant has been trading in the form of manufacturing and supplying the industrial facilities, etc. by being awarded a contract with the Plaintiff, etc. for the manufacture of the industrial facilities, etc. from the Plaintiff, etc. and being awarded a contract for the manufacture of the industrial facilities, etc. by the Plaintiff, etc.

B. (1) On May 30, 2013, the Plaintiff entered into a contract for the manufacture and supply of goods, etc. (i.e., the items listed below) from Scco Construction to Scco Construction, which are the transport facilities for Scco 2 dykes (STS).

hereinafter referred to as “instant facilities”

On the basis of the drawings presented to the Plaintiff, the Defendant requested the Defendant to make an estimate of the above manufacturing and processing of the equipment. The Defendant, based on the total of 216 tons of the materials required for the production, and the total of 589,408,000 won, including 12.3.5 T or 12.43.4.3.5 Domeny 15.3.40 4.3.40 Domeny 15.4.37.37 4.3.40 8.4.37 18.4.42.14.3 4.4.0 Domeny 13.4.4.14.14.14.14.6.14.14.14.30