대여금
1. The Defendant (Appointeds) KRW 721,875, KRW 550,00 to the Selection B, and KRW 8,236,250 to the Selection C, respectively.
1. Indication of Claim: On September 2014, the Plaintiff (Appointeds) and the designated parties leased construction equipment to J block work of Sejong Special Self-Governing City at the Defendant’s request.
The price for each construction equipment that the plaintiff (appointed party) and the appointed party shall receive from the defendant is the same as the amount stated in the above order.
Accordingly, the plaintiffs (Appointeds) and the designated parties seek to the defendant payment of the above equipment costs and the amount of money by 15% per annum under Article 3 (1) of the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from the day following the delivery of a copy of the complaint of this case to the full payment date.
2. Judgment by public notice (Article 208 (3) 3 of the Civil Procedure Act).