공사대금
1. Of the instant lawsuit, 23,051,869 won and damages for delay shall be dismissed.
2. The defendant.
1. Basic facts
A. Special conditions of the construction contract, such as the conclusion of the instant construction contract (Evidence A 1) 02. Amount of the construction contract: 2.7 billion won in daily amount
b.The actual cost of construction shall be 3.530,000 won (excluding VAT);
In addition to the construction contract amount, the actual cost of various interior installation costs, such as construction, civil engineering, electricity, machinery and equipment, fire fighting (electric, machinery), information and communication, water supply, waterworks, sewerage, GAS, parking facilities, and all other interior installation cost (friger, air conditioner, water conditioning, washing machine), the cost of the purchase of installation cost (frigering material consultation - frigering paper, books) and the cost of the cost of the household installation (friger, book) shall be responsible for and organized by the plaintiff for the loss report on the construction cost of various construction works (outstanding fee), other than the cost of the construction project, which is separate from the cost of the construction project.
06. A, B, and C shall be completed by the end of August, and completed by the end of December in cases of D, E, F, and G Dong.
Provided, That the completion schedule shall be changed according to the starting date and the date after the winter season.
1) The Defendant, who runs a construction business, was using the trade name “G” and changed the trade name “H” into “H” on July 2015. In order to newly build 7 Dong Dong (Adong-G Dong Dong) on the land outside C and six parcels of land in emulation, on March 25, 2015, the Defendant entered into a construction contract with the Plaintiff on April 15 (on March 25, 2015, and September 30, 2015 on the date of completion (excluding rain and winter period), the contract amount of 2,700,000,000 won (excluding value-added tax) (hereinafter “instant construction contract”).
The main contents of the special agreement are as follows. (2) When it is difficult for the Plaintiff and the Defendant to start the construction of the seven buildings at once due to loan, etc., each Dong of the instant housing consists of about 14 m2 to 16 m2 in exclusive use area, and A Dong has underground shops besides the above 17 m2 in addition to the above m2.
(3) Reference to Paragraph (3) was completed first, and the remaining three buildings were agreed to begin later, and accordingly, the Plaintiff on the instant housing around May 21, 2015.