beta
(영문) 대구지방법원 2019.11.21 2019가합337

손해배상(기)

Text

1. The defendant shall pay 328,00,000 won to the plaintiff and 12% per annum from July 16, 2019 to the day of complete payment.

Reasons

1. Indication of claims: To be as specified in attached Form 1;

2. Grounds for determination: Articles 208 (3) 1 and 257 of the Civil Procedure Act;

3. The Plaintiff seeking payment of damages for delay calculated at the rate of 15% per annum from the day following the delivery of a copy of the complaint of this case to the day of full payment. However, as the provisions on statutory interest rate of Article 3(1) main sentence of Article 3(2) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings were amended by Presidential Decree No. 29768 on May 21, 2019, pursuant to Article 2(2) of the Addenda (Presidential Decree No. 29768, May 21, 2019), where the pleading is terminated after June 1, 2019, the Plaintiff shall apply 15% per annum interest rate of the previous provisions until May 31, 2019, and from June 1, 2019 to the day of full payment, 20% per annum interest rate of 12% per annum interest rate of the previous provisions under the amended provisions, where a judgment is pronounced without pleading, the subsequent judgment shall be served with the date of full payment.