건물명도
1. The Defendant: (a) at KRW 4,059,284 from the Plaintiff, set forth in attached Form 1, 2, 3, 4, 198.46 square meters among the buildings 1,198.46 square meters in attached Table 1, 198.
1. On February 27, 2012, the Plaintiff indicated the claim and leased the part (i) of the order under Paragraph (1) of this Article (hereinafter “instant building”) to the Defendant as KRW 10 million in deposit, KRW 36 months in lease, and KRW 300,000 in rent.
However, from September 2015, the defendant did not pay rent, public charges, etc.
Accordingly, the Plaintiff redeems the remainder after deducting the overdue rent and public imposts, etc. from the deposit, and at the same time seeks to remove the building under Article 2 of the order of unlawful construction. 2. Judgment without holding any pleadings (Articles 208(3)1 and 257 of the Civil Procedure Act)