물품대금
1. The Defendant’s KRW 180,930,00 for the Plaintiff and KRW 6% per annum from May 1, 2015 to November 30, 2015.
1. Basic facts
A. The Plaintiff is a company for the purpose of manufacturing and selling automation machinery, etc., and the Defendant is a company that runs the business of processing and processing advertising machinery, etc.
B. On April 12, 2011, the Plaintiff entered into a contract with the Defendant for the supply of goods (hereinafter “instant primary contract”) with respect to the production and supply of C (Fiber Marler Machine, hereinafter “instant machinery”).
Article 1 Item 1) Item 1 of the subject matter of a contract: The payment period of 1 Form 3): advance payment of contract amount of KRW 620,00,000 (value-Added Tax) (50%) of KRW 310,000 after the contract of KRW 50,000 (after the approval of the production history of May 1, 201), the first intermediate payment (12.5%) of KRW 77,50,000 (after the approval of the entire design of June 30, 201), the Plaintiff shall complete the second intermediate payment (12.5%) of KRW 77,50,000 (after the approval of the entire design of June 30, 201), and the Plaintiff shall conduct an interim inspection of KRW 50,00 (12.5%) of KRW 10,000 after the completion of the interim inspection of the supply of the equipment of KRW 305,70,000 (15,275,75,701).
2) The Plaintiff shall deliver the pertinent goods to the designated delivery place. 4) The Plaintiff considers that the goods have been delivered to the place designated by the Defendant within the delivery date specified in the contract or the purchase delivery form and passed an inspection by the tallyman designated by the Defendant, and that the delivery was completed with the Defendant’s approval that there is no error in the installation trial, and the Plaintiff cannot raise an objection against the Defendant’s failure to pass the inspection.
5) Other detailed matters shall be in accordance with the purchase specifications. Article 10 (In the event that the Plaintiff fails to complete the delivery within the due date specified in this contract document, the Plaintiff shall bear the penalty for delay equivalent to 3/1,000 of the total contract amount per day of delayed due to reasons attributable to the delay.