beta
(영문) 수원지방법원안산지원 2015.11.27 2015가단16606

물품대금

Text

1. The Defendants jointly and severally liable to the Plaintiff for KRW 34,658,260 and Defendant Southern Construction Co., Ltd. on October 2015.

Reasons

1. Indication of claims: It shall be as shown in attached Form; and

2. Judgment without holding any pleadings (Articles 208 (3) 1 and 257 of the Civil Procedure Act);

3. Pursuant to Article 3(1) main sentence of Article 3(1) of the Act on Special Cases concerning the Promotion, etc. of Legal Proceedings on Part of Dismissal (wholly amended by Presidential Decree No. 26553, Sep. 25, 2015; effective October 1, 2015) and Article 2(2) of the Addenda, the part demanding payment of damages for delay calculated at the rate exceeding 15% per annum after October 1, 2015 among the Plaintiff’s claims is dismissed.