대여금
1. The Plaintiff:
A. Defendant A Co., Ltd. shall be KRW 300,000,000 and this shall be from December 4, 2012 to February 20, 2017.
The Plaintiff is a company that manufactures semiconductors, L.E.D. equipment, etc., Defendant A Co., Ltd. (hereinafter “Defendant Co., Ltd.”) is a company that manufactures semiconductor wafers, etc., and Defendant B is an internal director of the Defendant Co., Ltd.
On November 24, 2011, the Plaintiff decided to lend KRW 300 million to the Defendant Company without interest within one year from the date of borrowing the repayment (hereinafter referred to as “instant loan”), paid KRW 100 million on December 9, 201, and KRW 300 million on December 16, 201, and Defendant B guaranteed the Defendant Company’s obligation to repay the instant loan.
As the Defendant Company was unable to repay the instant loan due, the Plaintiff and the Defendant Company extended the final repayment period on December 13, 2012 to April 30, 2013; however, the Plaintiff and the Defendant Company shall pay interest at an annual rate of 7% per annum on the principal amount from December 4, 2012 to the date of full payment (hereinafter “instant promise”) and notarized the following (hereinafter “instant promise”).
As to the Plaintiff (the same shall apply in this Schedule), Defendant Company (hereinafter the same shall apply in this Schedule), and the same shall apply in this Schedule.
1. On November 24, 201, “A” and “B” promise to pay B the principal and interest to B by applying the annual interest of KRW 300 million from December 4, 201 to April 30, 201, when preparing a certificate of borrowing KRW 300 million from Company B, but the repayment date was December 4, 2012 due to the circumstances of “B”, and due to the failure to pay the principal and interest to B, by applying the annual interest of KRW 300 million from December 4, 2012 to April 30, 2013.
2. B shall implement paragraph 1 by April 30, 2013, and the repayment shall be made in two installments of the principal and interest.
The primary due date of repayment of principal and interest and the payment method of principal and interest shall be paid 200 million won and 7% interest per annum on the date of receipt of the secondary intermediate payment of Eul in the supplement (Sold-Cat Machine supply contract).
The second installment shall pay interest of KRW 100 million and interest of KRW 7% per annum until April 30, 2013.