beta
(영문) 울산지방법원 2019.06.20 2019가합18

대여금

Text

1. The Defendant: 30% per annum from January 24, 2008 to July 14, 2014, and July 15, 2014, to the Plaintiff. < Amended by Presidential Decree No. 2520, Jul. 15, 2014>

Reasons

1. Indication of claim;

A. On January 24, 2008, the Plaintiff: (a) decided on January 24, 2008, KRW 220 million as interest rateing to KRW 70 million per annum; and (b) on January 24, 2009, lent the loan to the Plaintiff.

B. Therefore, as the Defendant seeks from January 24, 2008 to July 14, 2014, the Plaintiff is obligated to pay to the Plaintiff 30% per annum as stipulated in the Rules on the Interest Limitation Act and the Interest Limitation Act (amended by Presidential Decree No. 25376, Jun. 11, 2014); and 25% per annum as to the maximum interest rate under Article 2(1) of the former Interest Limitation Act from July 15, 2014 to March 12, 2019 (amended by Presidential Decree No. 28413, Nov. 7, 2017); and damages for delay calculated at 15% per annum as to the maximum interest rate under Article 2(1) of the former Interest Limitation Act (amended by Presidential Decree No. 28413, Jun. 11, 2014).

2. Article 208 (3) 3 of the Civil Procedure Act (Judgment by public notice) of the applicable provisions of Acts;