(영문) 대전지방법원홍성지원 2014.01.23 2012가합850

공사대금

Text

1. The Defendant: (a) 29,800,000 won for Plaintiff B; (b) 2,700,000 won for Plaintiff C; and (c) 17,400,000 won for Plaintiff C Construction Co., Ltd.; and

Reasons

1. Basic facts

A. The instant pension construction 1) R, the husband of Defendant Q Q, is the husband of the Defendant’s representative director, on December 20, 2010, and Boli-si penta (hereinafter “instant pension”) between S on December 20, 2010.

(2) As to the newly constructed construction, the following agreements (hereinafter referred to as “instant agreement”) shall be made:

was drawn up.

1. The name of the construction work: Bosa City Do pent-built construction work;

3.The owner R and S shall make every effort to carry out the above construction to ensure that the construction is carried out smoothly.

4-1. S shall establish a work plan in advance to ensure the smooth progress of the Corporation, supply and demand materials and human resources necessary for the Corporation, report the work execution budget to R and execute the construction after obtaining approval.

4-2.S shall establish a monthly and weekly work programme, manage it so as not to delay the construction, and report to R on the progress and plan of each week.

4-3. The selection of subcontractors shall be an enterprise which is determined by R by submitting to the R two or more persons (based on three enterprises) a person to perform the construction work in good faith.

4-4.R shall execute funds required for the progress of the work and shall secure and execute funds so as not to delay the work from the funds.

5.R shall pay S 5,00,000 per month in advance on the 20th day of each month as the service cost for the progress of the construction project and shall provide S with accommodation of a person responsible for the site permanently stationed at the site.

S shall select one person in charge of the site and reside at the site to conduct and manage the project.

2) S shall be General Construction Co., Ltd. (hereinafter referred to as “General Construction Construction Construction”).

) The instant penty construction project shall be carried out with a comprehensive construction license granted, but the total construction cost of 3% shall be paid in terms of fees, etc. shall be paid for the penty Construction. On December 20, 2010, the instant penty Construction project under the Defendant’s name shall be KRW 450,000,000 for the construction cost of the instant penty Construction project (excluding value-added tax and the construction period from January 3, 201 to May 31, 201).