지체상금
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
1. Determination as to the cause of claim
A. The Plaintiff’s assertion 1) The Plaintiff’s assertion between the Defendant and the Defendant on March 26, 2013 (hereinafter “instant hotel”).
(2) As the Plaintiff entered into a contract for construction of new machinery, the Plaintiff entered into a contract with the Plaintiff on the completion of construction of the said construction works at 176,297,00 won (1,875,500,000 won) on December 29, 2014, and the completion date of construction at 0.1% until November 30, 2014. However, the Defendant asserted that the construction of the said machinery was completed on March 5, 2015, and delivered documents on completion inspection to the Plaintiff. Accordingly, the Defendant did not have the obligation to compensate the Plaintiff for delay for the damages for the period from November 30, 2014 to March 5, 2015 (1,875,500,000 won) on the completion date of construction works at 17,00,000 won (20,000 x1,094, which is the date of completion of construction works at 20,000).
B. 1 per determination, if the construction was discontinued and the last process intended to be completed is not completed, the construction shall be deemed to have been completed, but the construction shall also be the last process intended to be completed.