(영문) 대전지방법원 2016.01.14 2015가단220785

구상금

Text

1. The defendant shall be jointly and severally liable to the plaintiff with B, C, D, Large Construction Co., Ltd., and Chungcheong Industry Development Co., Ltd.

Reasons

1. Indication of claims: It shall be as shown in attached Form; and

2. Judgment without holding any pleadings (Article 208 (3) 1 of the Civil Procedure Act);

3. The amended provision on statutory interest rate under the main sentence of Article 3 (1) of the Act on Special Cases concerning Expedition, etc. of Legal Proceedings (Presidential Decree No. 26553) was promulgated on September 25, 2015 and enforced on October 1, 2015, the Plaintiff’s claim for damages for delay was partially dismissed.