beta
(영문) 광주지방법원 목포지원 2017.01.12 2015가합10061

손해배상(기)

Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. On November 13, 2012, the Plaintiff entered into a contract for construction works, on the land outside B and six parcels of land (hereinafter “instant building”) on which the Plaintiff contracted to the Defendant for the new construction work (hereinafter “instant construction work”) by October 30, 2013.

(hereinafter “instant contract”). After that, the Plaintiff and the Defendant extended the construction period by January 31, 2014, but extended the construction period by January 31, 2014, around January 30, 2014, the construction period was again extended by April 30, 2014.

The main contents of the instant contract are as follows.

(A) “A” means the Plaintiff and the Defendant. 【A” (Standard Contract for Private Construction Works)

3. Date of commencement: Value-added tax of KRW 4,64,00,000 on October 35, 2013: 464,00,000 for value-added tax of KRW 5,104,00 on December 4, 2012;

7. Advance payment: Marking under Article 11 on the special agreement.

8. Endd portion: 11.No. 0.1% (matters of special agreement) for liquidated damages: The timing for the payment of liquidated damages shall be paid as follows:

The contents of the classification shall be 765,600,000 won after the completion of 60 days after the completion of 610,40,000 won after the completion of 60 days after the completion of 60,000 won after the completion of 510,40,000 won after the completion of 60 days after the completion of 60 days after the completion of 765,60,600 won after the completion of 765,60,000 won after the completion of 765,60,60,000 won after the completion of 765,60,60,000 won after the completion of 765,60,60,000 won after the removal of concrete on the 3rd floor.

Article 30 (Compensation for Delay) (1) "B" shall be calculated by multiplying the contract price by the delayed rate for delay in the contract for each number of days when the construction work has not been completed within the deadline for completion.