임금
1. The Defendant (Counterclaim Plaintiff) shall pay to the Plaintiff (Counterclaim Defendant) KRW 28,430,970 as well as the full payment from March 13, 2018.
1. Around September 2015, the Defendant, at the time of filing the instant lawsuit, awarded a contract to the Plaintiff for reinforced concrete construction among the new construction works of the petition-gu C commercial building, and the Plaintiff completed the said construction before filing the instant lawsuit. The Defendant did not dispute between the parties, or can be recognized in full view of the purport of the entries and arguments in the evidence A Nos. 1 and 2.
Therefore, the Defendant is obligated to pay to the Plaintiff damages for delay calculated at the rate of 15% per annum from March 13, 2018 to the day of full payment, as the Plaintiff seeks.
2. The Defendant asserts that, around 2016, the Defendant paid the Plaintiff construction price exceeding KRW 42,440,043 in excess of the total of KRW 5,685,693 in relation to reinforced concrete construction among the new construction works of the D Elementary School located in Sejong Special Self-Governing City and KRW 36,754,350 in relation to the new construction works of the Health Insurance Corporation, and KRW 36,440,043 in excess of the total of KRW 42,440,043 in relation to the construction works of the 42,430,970 in excess of the unpaid construction price, the Plaintiff shall return the remainder of KRW 14,09
The evidence submitted by the defendant alone is insufficient to deem that the defendant paid the construction cost in excess of the construction cost as asserted by the defendant, and there is no other evidence to support this. Therefore, the defendant's above assertion is without merit.
3. In conclusion, the plaintiff's claim on the principal lawsuit is justified, and the defendant's counterclaim is dismissed as it is without merit. It is so decided as per Disposition.