(영문) 전주지방법원 2017.04.27 2016가합1143

공사대금

Text

1. The Defendants shall jointly and severally serve as the Plaintiff KRW 175,591,109 and as a result, from December 31, 2016 to April 27, 2017.

Reasons

1. Basic facts

A. 1) The Defendants concluded a construction contract and a subcontract agreement

(C) On July 2010, the Saemangeum Flood Control Project (hereinafter referred to as the “the original contract project in this case”) shall be organized by a joint supply and demand organization consisting of representatives of third and third-party land and construction works between the Korea Rural Community Corporation and the Korea Rural Community Corporation.

(2) On November 7, 2012, the Plaintiff entered into a subcontract with the construction period from November 7, 2012 to February 28, 2016, and the contract amount of KRW 2,502,500,000, among the instant prime contract construction works, and changed the said contract from November 7, 2012 to April 30, 2016 to April 30, 2016.

(3) On November 27, 2012, the Plaintiff entered into a contract for the purchase of goods to supply a total of KRW 747,626,000 with respect to the instant prime contract (hereinafter “instant purchase contract”). The Plaintiff refers to the “instant subcontract” and “the instant purchase contract” and “the instant purchase contract.”

(4) From January 6, 2014 to February 3, 2016, the Plaintiff received KRW 2,243,696,000 as the sum of the price under each of the instant contracts as follows.

1. The amount of KRW 319,191,00 on January 6, 2014, 201: KRW 260,00 on March 25, 2014; KRW 366,867,00 on April 2, 2014; KRW 40,000 on June 19, 2014; KRW 50,000 on June 23, 2015; KRW 640,131,00 on May 23, 2015; KRW 639,981,00 on July 22, 2015; KRW 630,00 on July 39, 2015; KRW 10,000 on KRW 7.90,00 on July 29, 2015; KRW 10,000 on August 10, 2010; and

B. On September 3, 2015, the 13th anniversary of the commencement of the 3rd anniversary of the rehabilitation procedure, the Seoul Central District Court rendered a decision to authorize the rehabilitation plan on February 26, 2016, following the commencement decision of the rehabilitation procedure pursuant to the Seoul Central District Court Decision 2015 Gohap1025.