beta
(영문) 서울북부지방법원 2019.06.25 2018나1764

공사비

Text

1. Of the judgment of the court of first instance, the part against the defendant exceeding the amount ordered to be paid below shall be revoked.

Reasons

1. Under each of the following facts, facts are either disputed between the parties, or acknowledged based on Gap evidence 1 through 4, Gap evidence 11, 12, 14, 15, Eul evidence 1-1, 2, Eul evidence 3, Eul evidence 9-1 through 4, Eul evidence 26-1, 2, Eul evidence 27-1, 27-6, and Eul evidence 27-1 through 6, and the whole purport of the pleadings.

On February 18, 2017, the Plaintiff entered into a contract for construction works with the Defendant, setting the construction cost of KRW 150 million from February 21, 2017 to March 20, 2017 with the Seongbuk-gu Seoul building D (hereinafter “instant building”) E, F, G, and H (hereinafter “instant construction works”) at the cost of construction KRW 150 million from February 21, 2017 to March 20, 2017 (hereinafter “instant contract”).

B. The building of this case has two rooms on each floor, and there are three rooms, three rooms, and three rooms in each room for up to the fourth floor, and one room for each floor has not been indicated in the direction of the ground plan attached to the north (A, Nos. 3, 15, and evidence Nos. 26-1, and 26-2, etc., but the left side of the ground plan as specified by the Plaintiff, as stated by the Plaintiff, refers to the left side, the upper side of the ground plan is referred to as the "west", and the upper side is referred to as the "west side", the ground plan is referred to as the "west side", and the right side of the ground plan is referred to as the "Northwest side", each floor is the structure where the second room for the second floor is located in the south side, five floors (E, F), six (Ghoho Lake, Hhoho Lake, one room, and one room for the outside, and one room for rescue and relief of both the two rooms.

C. The Defendant filed a report on the extension of 24.32 square meters and 23.41 square meters, respectively, by installing two rooms at a location 2.35 meters away from the north side outer wall of the instant building (Eho, Fho Lake) and expanding the area of the living room and the main room. The Defendant filed a report on the commencement of construction on March 15, 2017, and obtained approval for use on April 12, 2017.

The Plaintiff’s construction from February 21, 2017, which was the commencement date stipulated in the instant contract, is proceeding with the instant construction from February 21, 2017, and the building E, F, G, and H are as follows.