(영문) 창원지방법원 진주지원 2018.05.30 2016가단2648

공사대금

Text

The Defendant-Counterclaim Plaintiff (Counterclaim Defendant) is a solar power plant with the size of 1101 square meters and its ground prior to the Cheongnam-gun, Busan-do.

Reasons

A principal lawsuit and a counterclaim shall be deemed simultaneously.

1. The facts below the basis facts do not conflict between the parties, or can be acknowledged in full view of the whole purport of the pleadings in each of the statements in Gap evidence Nos. 1 to 14, Eul evidence No. 1 to 5, 7, and 11 (including the cases where there are serial numbers).

On January 8, 2014, the Plaintiff and the Defendant concluded an engineering service contract (hereinafter “instant service contract”) with the effect that “service period: the service period is from January 8, 2014 to March 31, 2014 (from January 8, 2014 to March 31, 2014, the contract amount of KRW 35,000 (value-added tax separate contract deposit KRW 20 million is paid at the time of the contract, the balance of KRW 15 million is paid after the completion of the permission) to the Plaintiff, the Plaintiff and the Defendant, the Defendant owned, in addition to the instant service contract, entered into an engineering service contract with the effect that “the construction of solar power plants” means either the contract amount of KRW 20,000,00,000,000,000,000,000,000,000 won, which is KRW 16,000,000,000,00.

(1) An additional special agreement shall be completed to cover the investment cost of more than 100 kws above solar power plants (250,000,000) with the construction of a mushroom cultivation house (550 m2) in the Cheongsi-gun, Busan (1,101 m2).

(2) The investment cost of KRW 250,000,000 (Won 250,000) shall be completed 100 kw annually by the bank on the loan of only C real estate and facilities.

"....."

B. February 14, 2014