beta
(영문) 수원지방법원평택지원 2019.01.18 2018가단6667

대여금

Text

1. The defendant is calculated by the ratio of KRW 100 million to KRW 2% per month from October 25, 2008 to the full payment.

Reasons

[Indication of Claim] Around September 25, 2008, the Plaintiff loaned KRW 100 million to the Defendant by setting the due date as October 24, 2008, and damages for delay as 2.5% per month, and was drafted by the Defendant a notarial deed of a monetary loan contract for consumption.

Since the completion of the extinctive prescription is imminent after about 10 years have elapsed since the maturity date, the instant lawsuit is filed for the interruption of the extinctive prescription, and damages for delay shall be raised at the rate of 2% per month [based on recognition] by public notice (Article 208(3)3 of the Civil Procedure Act).