(영문) 서울중앙지방법원 2015.04.28 2015가합507589

구상금

Text

1. The Defendants jointly and severally against the Plaintiff

A. From December 17, 2014 to March 9, 2015, KRW 136,491,630 and its interest.

Reasons

1. On August 8, 2014, the Plaintiff indicated the claim and Pungsung Commercial Co., Ltd. (hereinafter “Defendant Company”) concluded a credit guarantee agreement and jointly and severally guaranteed the obligation under the said credit guarantee agreement against the Plaintiff by Defendant A, and then, on December 16, 2014, the Plaintiff claimed performance against the Defendants, the primary debtor and the joint and several sureties, with respect to the amount of money, substitute payment, and damages for delay that the Plaintiff acquired by subrogation for the Defendant Company’s loan to the Industrial Bank of Korea on December 16, 2014,

2. Articles 208 (3) 1 and 257 of the Civil Procedure Act of the applicable provisions of Acts;