(영문) 대구지방법원 2018.06.15 2017구합23805

입찰참가 제한처분 취소청구

Text

1. The Defendant’s disposition of sanction against unjust enterprisers (five months) against the Plaintiff on October 16, 2017 shall be revoked.

2. The costs of lawsuit shall be.

Reasons

1. Details of the disposition;

A. The Plaintiff is a company that has undertaken construction business, civil engineering business, general construction business, etc. as its intended business from January 17, 1995 to 238, Daegu Suwon-dong-ro (China-dong).

B. On June 9, 2017, the Plaintiff participated in the bid for the construction project to build a revolving intersection in Daegu Metropolitan City A-gu (hereinafter “the construction project to build a revolving intersection”) ordered by the Defendant and won the bid, and entered into a construction contract with the Defendant as follows (hereinafter “instant contract”).

Construction name: The contract price for the installation of an intersection in Daegu-gu Seoul Metropolitan City: 102,549,000 won on the date of commencement: June 15, 2017: the date of completion: September 12, 2017: 0.05% on the date of commencement: 90 days from the date of commencement;

C. B is a construction supervisor at the construction site of the construction site of the revolving intersection, and on June 29, 2017, visiting the site to supervise the Plaintiff’s progress of construction works.

Since June 29, 2017, the defendant

8. By the 17th day, the Plaintiff sent an official door to the following: (a) replacement of an on-site agent on a total of five occasions; (b) suspension of installation of a revolving intersection until that time; and (c) submission of countermeasures, construction plans, etc. for poor operations.

The details of the date on July 29, 2017: (a) the request for submission of a construction plan for a process in which the request for replacement of a site agent is insufficient on July 10, 2017; and (b) the request for submission of a construction plan for a process in which the request for replacement of a site agent is insufficient on July 28, 2017; and (c) the request for submission of a construction plan for a process in which the request for replacement of a site agent is insufficient on July 28, 2017; and (d) the request for submission of a construction plan for a process in which the request for replacement of a site agent is insufficient on August 10, 2017; and (e) the request for submission of a plan and the implementation of a construction project for a process in which the request for cancellation of the contract of the project department is insufficient on August 17, 2017.

(d) however.