beta
(영문) 창원지방법원 2018.11.08 2017가합162

공사대금

Text

1. The plaintiff (Counterclaim defendant)'s main claim and the defendant (Counterclaim plaintiff)'s counterclaim are dismissed, respectively.

2. Of the costs of lawsuit.

Reasons

(b)be paid under the pretext of land interest, land interest, land interest, etc.;

(f) On May 1, 2016, the Defendant drafted a contract document (No. 2) signed on May 1, 2016 with respect to E and the instant construction, stating the following: < Amended by Presidential Decree No. 27170, May 1, 2016>

3. Date of commencement: The scheduled date of completion on February 4, 2016: Contract amount on August 15, 2016: Value-added tax of KRW 1,031,724,000 separately (excluding 6% of the construction cost at the time of tax-free workplace).

6. Contract bond: 10% of the contract amount;

7. Advance: 400,000 won; and

8. End amount: Statement of the special agreement. 10. Liability for warranty (in the case of a multi-functional type, the classification by type of work) and 39% of the cost of reinforced concrete construction work: 4.8% of the waterproof construction work in 10,000,000 won: 50,000,000 won and 56.2% of other construction work: 581,724,000 won: 581,724,000 won: Number of delayed days * 3/1,000 of the contract amount * Other matters in accordance with the contract special specifications: The defendant's agent C: the agent as joint guarantor

1. The scope of the construction works: Incidental civil construction works, underground base destruction works, construction works for housing of one story to five stories above ground, and works incidental thereto;

3. The construction project, as a total contract method, may increase or decrease the construction volume, but there is no change in the contract amount even when the construction volume increase or monitoring. 21. The Plaintiff shall perform the responsibility with the amount of money of KRW 3,600,000/pact, including interest on loans (the amount invested in the construction cost) by the Defendant’s guarantee and construction design and supervision expenses, and the cost of removing the existing structure (the changed area at the time of design change)* 3,60

2. On the other hand, G agrees on April 30, 2016 that "the defendant shall complete the responsible execution of the instant construction work."

I prepared and provided ‘the statement of performance' and ‘the statement of joint and several guarantee'.

G. On May 11, 2016, the Plaintiff (i.e., the Plaintiff) following the process of the instant construction.