beta
(영문) 전주지방법원 군산지원 2016.11.03 2016고합108

특정경제범죄가중처벌등에관한법률위반(사기)등

Text

A defendant shall be punished by imprisonment for three years.

Reasons

Punishment of the crime

The defendant is the representative director of the corporation E (F on July 11, 2013) that operates the business of manufacturing processed grain products in Gunsan-si D. The defendant is the representative director of the corporation E (E).

1. The Act on the Aggravated Punishment, etc. of Specific Economic Crimes (Fraud) and the Act on the Budgeting and Management of Subsidies and the Act on the Aggravated Punishment, etc. of Specific Economic Crimes- the Act on the Aggravated Punishment, etc. of Aggravated Punishment and the Act on the Aggravated Punishment, etc. of Aggravated Punishment and the Act on the Aggravated Punishment, etc. of Aggravated Punishment and the Act on the Aggravated Punishment and Management of Subsidies to Industry Co., Ltd. were selected as a subsidized project operator in April 21, 2009 by the defendant. The major contents of the project were to produce specialized items by obtaining the national subsidy of KRW 500,000,000,000, in total, and KRW 1,000,000,000, in terms of the above self-paid and the subsidies to be provided as “a mixture for the processing of White rice reporting, a building, and a manufacturing facility for subsidies (hereinafter “subsidies facility”).

The Defendant, even though he did not have the intent or ability to use his own contributions for the subsidy project and did not intend to use the entire subsidy, did not intend to use the subsidy for the subsidy project, received the loan from the financial institution on the condition that all of the subsidy facilities subject to disposal restrictions are subsequently offered as security, and, by submitting false data, such as a written contract in which the amount of the actual contract amount is unsatisfed between the subsidy facility supplier and the subsidy facility provider.

On October 12, 2009, the Defendant promised to receive in advance a return from G Co., Ltd. (hereinafter referred to as “G”) to receive 600,000,000 won from G Co., Ltd. (hereinafter referred to as “G”) and the construction cost of which are KRW 1,00,000.

In addition, around October 2009, around 20.