(영문) 서울중앙지방법원 2013.04.18 2012가합518861

구상금

Text

1. The Plaintiff:

A. The above amount is the 62,205,426 won and the above defendant's joint and several factors.

Reasons

1. Basic facts

A. 1) The Korea National Housing Corporation (Korea National Housing Corporation and the Korea Land Corporation were merged with the Plaintiff on October 1, 2009.

hereinafter referred to as "Plaintiff"

2) The 17 apartment complexes of Suwon-si, Suwon-si, Suwon-si, 861 Chowon-dong, 17 apartment complexes (hereinafter referred to as the “instant apartment buildings”).

2) The construction of the apartment of this case was contracted by the Plaintiff to the contractor for the construction of the second section of the apartment of this case, and the construction of the main section of the Defendant Gyeyang-do is the joint and several surety who guaranteed the performance of its duties as the contractor for the construction of the Chungcheong Day and the construction of the Gyeong-do. The Defendant Seoul Guarantee Insurance is the defect guarantee insurance for the construction of the Chungcheong Day and the construction of the Gyeong-do.

3) On October 11, 2004, Defendant Chungcheongnam-nam Company (hereinafter “Gannam Construction Company”) merged with another company.

) The contractor who was awarded a contract with the Plaintiff for a new construction of 3 sections of the apartment of this case, and the brick construction [the manager is the manager A of the rehabilitation debtor A (hereinafter referred to as the “Defendant A”) who is the lawsuit subject to the lawsuit against the Defendant Marsan Construction Co., Ltd.

4) Defendant Sung Il Construction Co., Ltd. receives a contract from the Plaintiff for the new construction of the instant apartment site from the Plaintiff, and Daeyang Construction Co., Ltd. (hereinafter “Defendant B”). The manager is the manager B (hereinafter “Defendant B”) of the Korea Rehabilitation Corporation (hereinafter “Defendant Yangyang Construction Co.,, Ltd.”).

(1) The defendant Construction Mutual Aid Association is a joint and several surety that guarantees the performance of its duties as the contractor of the defendant Sung Il Construction, and the defendant Construction Mutual Aid Association is a warranty bond for the part of the execution of the defendant Sung Il Construction.

B. On 198, the Plaintiff entered into a contract for work, etc. is Nonparty Woo-il Construction around 1998.