구상금
1. The Defendants are jointly and severally liable to the Plaintiff for KRW 27,061,703 and KRW 23,215,617 among them. From June 25, 2004 to August 9, 2004.
The Plaintiff has a claim against the Defendants based on a final judgment of an amount equivalent to 18% per annum from June 25, 2004 to August 9, 2004 with respect to KRW 26,037,696 and KRW 26,034,766 among them, and a final judgment of an amount equivalent to 20% per annum from the next day to the date of full payment (the Gwangju District Court Decision 2004Da52984, Nov. 2, 2004).
On June 28, 2013, the Plaintiff received reimbursement of KRW 2,819,149 from the Defendant and appropriated it to the principal. The penalty for attempted penalty additionally incurred thereafter is KRW 2,930, and the final delay penalty for the said repayment is KRW 3,843,156, and the interest rate for delay is KRW 18% per annum.
[Grounds for recognition] The facts without dispute, Gap evidence 1-4, and the purport of the whole pleadings are as follows: (i) the defendants are jointly and severally liable to pay 27,061,703 won (26,034,766 won of the first principal (26,034,766 won of the principal) - repayment delay penalty of KRW 2,930 of the penalty for non-payment of KRW 2,930 of the penalty for non-payment of KRW 2,819,149 (2,819,149) and the remaining principal (23,215,617 won of the last principal (26,034,766 of the principal) from June 25, 2004 to August 9, 2004; and (ii) the next day to the date of repayment of the principal is 2,819,149 won of the remainder.
The plaintiff's claim is justified, and it is so decided as per Disposition.