손해배상(기)
1. The Defendant’s KRW 308,000,000 and its related amount are 5% per annum from July 10, 2012 to April 12, 2016 to the Plaintiff.
1. The description of “the cause of the modified claim” in the attached Form to the description of the claim is identical to the description of “the cause of the modified claim.”
2. Article 208 (3) 3 of the Civil Procedure Act (Judgment by public notice) of the applicable provisions of Acts;
3. The statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases concerning Expedition, etc. of Legal Proceedings, which was amended on September 25, 2015 and enforced on October 1, 2015 (Presidential Decree No. 26553, Sept. 25, 2015) is applied to damages for delay by applying 15% per annum to the damages for delay from the date following the date of delivery of a copy of the application for change of the claim and the cause of claim as of April 8, 2016 until the date of full payment, and the excess shall be dismissed.
(P) Since the interest rate of delay damages is reduced due to the amendment of the Act and subordinate statutes, the conjunctive claim is not judged separately, and the costs of the lawsuit shall be borne by the defendant in accordance with the proviso of Article 101 of the Civil Procedure Act).