A defendant shall be punished by imprisonment for one year.

However, the execution of the above punishment shall be suspended for a period of two years from the date this judgment becomes final and conclusive.

Reasons

Punishment of the crime

[criminal history] On January 18, 2018, the Defendant was sentenced to 8 months of imprisonment with prison labor and 2 years of suspended execution for violating the Creation and Management of Forest Resources Act, etc. in the Gwangju District Court’s Netcheon Branch on January 18, 2018, and the judgment was finalized on September 18, 2018.

[2] The Defendant is a person who establishes and operates a limited company E with limited liability in order to obtain a bid for an afforestation project ordered by a public office in around 2013.

The Defendant, upon delegation by the forest owner, engaged in the “forest management by proxy,” and completed an “afforestation project” and “afforesting project” and “afforesting project,” under which the victims who did not delegate the forest management to the Defendant, who were the forest owners, forged the “acting management contract”, “a power of attorney”, and “an application for authorization of the forest management plan,” and submitted the former Military Service to obtain authorization for the forest management plan, sell the victims’ forest without permission, and without permission, sell the victims’ forest.

The number of old military forces applied for subsidies, deceiving the head of old military units to receive subsidies as if they were authorized by the management plan.

1. Crimes related to victim F (Gumnag G and H);

A. On September 24, 2014, the Defendant forged a private document “the proxy contract” and “the power of attorney” shall be deemed to be “the name F of the Gu, the address of the Gu,” and “the name F of the Gu, the forest owner” in the column for the forest where the substitute management contract is located, even though the Defendant did not have registered the register but the owner was the SiJ, the Si, and the Gu, the Si, the Dong, and the Si, the victim owned by the present manager, and F, even though he did not delegate or consent with respect to the proxy management of the Gu, the Gu, G, H, and H forest, and the term of contract from October 1, 2014 to October 1, 2024; and the proxy manager shall be deemed to be “the name F of the Gu, the address of the Gu,” and the “M (M) E, the construction business of the Gu, the NA, N.M. construction business of the NA.