beta
(영문) 대전지방법원서산지원 2015.05.14 2014가합2000500 (1)

추심금

Text

1. The Defendant shall pay to the Plaintiff KRW 187,459,535 and the interest rate of KRW 20% per annum from July 12, 2014 to the day of full payment.

Reasons

1. Basic facts

A. A. The Defendant: (a) a construction contract between the Defendant, Korea Industrial Development Co., Ltd., E&PP, and the Plaintiff); (b) the Defendant, on November 14, 201, is the Hanra Industrial Development Co., Ltd. (hereinafter “Korea-China Industrial Development”).

) On May 30, 2012, Hyundai Steel Power Plant Nos. 5, 6, 7, and 8 concluded a contract for the manufacturing of nitrogen oxides (including value-added tax) with the term “the contract amount of KRW 13.178 billion (including value-added tax) and the term of the contract from November 14, 201 to March 15, 201,” and the development of the Hanra Industry was on May 30, 201, S&P Co., Ltd. (hereinafter “S&P”).

The machinery of this case is referred to as the machinery of this case with 53.8 tons (FLUE GY YS YTSM 212.6 tons, SCR RE 263.6 tons, PLATS 263.6 tons, PLATFR STRM STR CURE 77.6 tons, hereinafter referred to as 'the machinery of this case'.

(2) On September 12, 2012, the Plaintiff paid 1 billion won (including value-added tax), the term of the contract, from May 30, 2012 to March 15, 2014, the construction work was set and subcontracted, and E&P re-subcontracted to the Plaintiff on July 9, 2012, KRW 900,000 (value-Added Tax Separate) contract amount of the instant mechanical manufacturing work. (2) around September 12, 2012, the Plaintiff suspended the remaining construction work under 90.1 ton of the instant machinery (hereinafter referred to as “five (5) and notified the Plaintiff of the termination of the subcontract price for the construction work on November 2, 2012, the Defendant directly applied for the final inspection of construction work from the Seoul Central District Court; and (2) the Defendant notified the Plaintiff of the termination of the subcontract price for the construction work on January 2, 2012 and the final inspection of construction work on March 1, 2012.