1. The defendant shall deliver to the plaintiff each real estate listed in the separate sheet.

2. The costs of the lawsuit are assessed against the defendant.

3...

Reasons

1. Determination as to the cause of claim

A. In fact, the Plaintiff is the Housing Redevelopment Improvement Project Association established by the head of Eunpyeong-gu Seoul Metropolitan Government for the purpose of implementing the Housing Redevelopment Improvement Project for the Eunpyeong-gu Seoul Metropolitan Government Group C.

On November 27, 2014, the head of Eunpyeong-gu Seoul Metropolitan Government Office approved and publicly announced a management and disposal plan for the plaintiff's housing redevelopment improvement project.

The defendant is the owner of each real estate listed in the separate sheet in the rearrangement project zone (hereinafter referred to as "the real estate in this case"), who is subject to cash settlement.

The Plaintiff filed an application for adjudication with the Seoul Special Metropolitan City Regional Land Expropriation Committee, as it did not reach an agreement on compensation for losses with the Defendant for each real estate.

On April 24, 2015, the Expropriation Committee decided on June 12, 2015 to expropriate the Defendant’s instant real estate as KRW 196,552,110 on the compensation for losses.

On May 28, 2015, the Plaintiff deposited the compensation on the ground that the Defendant refused to receive the compensation determined by the ruling.

[Reasons for Recognition] Unsatisfy, Gap 1 to 12, the purport of the whole pleadings

B. When the management and disposal plan stipulated in Article 49(3) of the Act on the Maintenance and Improvement of Urban Areas and Dwelling Conditions for Residents is publicly announced, use and profit-making by right holders, such as owners, superficies, persons having superficies, leasers, etc. against the previous land or buildings shall be suspended pursuant to Article 49(6) of the same Act, and the project implementer may use and profit from the former land or buildings (see, e.g., Supreme Court en banc Decision 91Da22094, Dec. 22, 1992; Supreme Court Decision 2009Da53635, May 27, 2010). Therefore, the defendant is obligated to deliver

2. The judgment of the defendant on the defendant's assertion is null and void because the plaintiff's deposit of compensation for losses under the adjudication of expropriation does not meet the deposit requirements under Article 487 of the Civil Code, and the plaintiff's deposit is made until