beta
(영문) 서울중앙지방법원 2019.08.28 2019가단16985

손해배상(기)

Text

1. The Defendants are jointly and severally liable to the Plaintiff for KRW 101,00,000 and the period from August 23, 2017 to August 28, 2019.

Reasons

1. Indication of claims: It shall be as shown in attached Form; and

2. Judgment without holding any pleadings (Article 208 (3) 1 of the Civil Procedure Act);

3. The statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings was amended on May 21, 2019 and enforced on June 1, 2019. Since the statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings was changed to 15% per annum until May 31, 2019 and 12% per annum from the next day, the portion exceeding 12% per annum out of the Plaintiff’s claim for delay damages after June 1, 2019 is dismissed.