beta
(영문) 서울서부지방법원 2016.06.10 2016가단203578

구상금

Text

1. The Defendant’s KRW 45,732,701 and KRW 45,732,360 among the Plaintiff’s KRW 12% per annum from June 16, 2014 to April 26, 2016.

Reasons

1. The description of the claim is as shown in the annexed sheet of claim

However, the “creditor” is deemed to be the “Plaintiff”, and the “debtor” shall be deemed to be the “Defendant”, and the payment order prior to the implementation of the instant lawsuit for Taesan Industries Co., Ltd. shall be finalized.

C. Meanwhile, on the first day for pleading of the instant case, the Plaintiff reduced the statutory interest rate, which serves as the basis for calculating damages for delay, from 20% per annum to 15% per annum.

2. Probation: Judgment by public notice (Article 208 (3) 3 of the Civil Procedure Act);