beta
(영문) 대전지방법원천안지원 2019.07.10 2017가단7916

손해배상(기)

Text

1. Defendant G Co., Ltd.: (a) 8,675,425 won to Plaintiff A; (b) 8,811,241 won to Plaintiff B; and (c) 7,842,803 won to Plaintiff C; and (d) the Plaintiff.

Reasons

1. Basic facts

A. The plaintiffs are each of the following sectional owners of the Dong-gu I-dong K-dong (hereinafter referred to as the "Saeng-dong, Dong-gu").

On October 27, 201, 201, Nos. 1 A L on the date of acquiring the ownership of the Nos. 1 and 2 B B on October 21, 2002, and on October 17, 201, 201, D No. 4 on July 4, 2017, 201, the ownership of the No. 5 E P on August 21, 2003, is owned on October 18, 201.

There are six and 546 households of “R apartment” (hereinafter “R apartment”) with the size of the two underground floors and the size of the 20th above ground on the ground located in the south-gu Q in the vicinity of the Dongdong-gu of this case. The site of this case (hereinafter “the site of this case”) is the site where Defendant F Co., Ltd. (hereinafter “Defendant F”) entered into a contract with S Co., Ltd. on March 2008 for the construction of the “T apartment building” with the size of 438 units of the 1st underground floor, the 19th ground level apartment building from S Co., Ltd. (hereinafter “Defendant F”), and from May 2008, the construction was suspended due to the payment of construction cost around September 2009.

C. Defendant H District Housing Association (hereinafter “Defendant H District Housing Association”) obtained authorization to establish an association on May 30, 2012, and completed the registration of ownership transfer on July 31, 2013 after purchasing the instant site and completing the registration of ownership transfer on June 30, 2014, and decided to newly construct the instant apartment on that date, Defendant H District Housing Association (hereinafter “Defendant H District Housing Association”) required U.S. to remove obstacles, such as dys, installed by Defendant F, from July 21, 2014 to November 30, 2014.

Defendant G Co., Ltd. (hereinafter “Defendant G”) contracted the Defendant Union with the soil st,206,70,000 construction cost of KRW 1,206,70,000 for the construction of the instant apartment, and entered into a contract for the second soil st,723,30,000 of construction cost around August 30, 2015, and performed the said soil st,723,30,000 from September 24, 2014 to May 30, 2016.

E. Meanwhile, around May 28, 2015, V and W Co., Ltd. are the construction and incidental civil engineering works except civil engineering works from the Defendant Partnership.