손실보상금증액등
1. The Defendant’s “the details of accommodation and compensation” as indicated in attached Form 1 to Plaintiff B, C, D, F, G, H, I, J, and L.
1. Details of ruling;
(a) Business name - Business name: M redevelopment and rearrangement project (hereinafter referred to as the "maintenance project in this case"): Defendant - Rearrangement project area: Defendant - Seoul: The determination and public announcement of urban renewal acceleration plans: O-Public announcement of Seoul Metropolitan Government on April 3, 2008; PPublic announcement of Seongbuk-gu Seoul Metropolitan Government on June 1, 2012
B. The Plaintiffs owned land, obstacles, etc. within the rearrangement zone (hereinafter collectively referred to as “land subject to expropriation”) as indicated in the column for “subject to expropriation” in attached Form 1 (hereinafter “the details of compensation money”).
C. The defendant from January 21, 2013 to the same year
2. Until February 28, 2010, the Plaintiffs filed an application for adjudication of expropriation with the Defendant on February 28, 2013, without complying with the agreement, on the grounds that the price of the land to be expropriated was low, and the written request was the same year.
3.4. Service was made to the Defendant.
The defendant filed an application for adjudication of expropriation on April 23, 2013, and the Seoul Special Metropolitan City Local Land Tribunal (hereinafter referred to as the "Expropriation Committee") on July 19, 2013 has the same year as the date of adjudication of expropriation.
9.6. The adjudication to expropriate the land, etc. subject to expropriation (hereinafter “the first adjudication”) was made on June, 201, but the said adjudication became null and void as the Defendant did not pay or deposit the compensation by September 6, 2013, which is the date of expropriation. Even after the conclusion, the Defendant filed an application for the adjudication of expropriation again on November 5, 2013 because it did not reach an agreement on compensation between the Plaintiffs and the Defendant. The Land Tribunal rendered the second adjudication on expropriation on February 14, 2014 (hereinafter “the second adjudication”). - Compensation date: April 4, 2014 - Compensation date: Based on each appraisal result of Samsung Appraisal Corporation, Samsung Appraisal Corporation, and Sam Chang Chang Chang (hereinafter collectively “appraisal”) (hereinafter collectively “adjudication”).