1. The Defendant’s KRW 70,441,626 as well as the Plaintiff’s annual rate from March 16, 2017 to May 25, 2018, and the following.

Reasons

1. Facts of recognition;

A. The plaintiff as the foundation A (hereinafter "the Foundation of this case")

B) As the insured, the instant foundation is located in Seocho-gu Seoul Metropolitan Government building B (hereinafter “instant building”).

(2) On October 7, 2016, the Defendant entered into a comprehensive building management contract with the Foundation from October 7, 2016 to October 7, 2017, with the insurance period of 16:00 to October 7, 2017. Of the security for the liability of the manager of the said insurance, the maximum amount of compensation per accident is KRW 100 million. (2) The Defendant is responsible for the management of all areas, such as the facilities, machinery, US dollars, and expenses of the instant building.

B. On January 29, 2017, the accident occurred. Around 06:20 on January 29, 2017, the driver discovered water flows out from the door of the instant building to the road, and contacted with the phone number on the building. As a result, the worker of the instant building confirmed the site, water leakage on the first floor of the instant building where the factory was installed, and water flows out on the first floor and the underground floor of the instant building. C, the E-sports center leased C was located on the first floor of the instant building; due to flood, the sports organization was planted, cut down a wooden part, and down a wooden part; and the damage, such as ice and ice, occurred. The damage inflicted upon C, etc. was the repair cost, the remaining water removal cost, 19,862,69, 197, 197, 197, 196, 297, 196, 196, 297, etc.).

The place where water leakage occurred was installed on December 5, 1992 at the location where hot spring water had been installed at the time of approval for the use of the building of this case. The entire owner of the building of this case, Samsan Mutual Savings and Finance Company, which is the former owner of the building of this case, was established between 192 and 202.