(영문) 청주지방법원영동지원 2015.10.16 2015가단709

청구이의

Text

1. The Defendant’s Cheongju District Court (Cheongju District Court Branch 2013Kadan590, Jun. 4, 2013) for the Defendant’s damages, etc.

Reasons

1. Facts of recognition;

A. 1) The Defendant filed a lawsuit against the Plaintiff seeking compensation, etc. for damages under the Youngju District Court’s Young-dong Branch 2013Kadan590, Jun. 4, 2013 (hereinafter “the instant recommendation order”). A) on June 4, 2013 in the instant case, the Plaintiff shall pay the Defendant the amount of KRW 1 million up to June 30, 2013, and KRW 1 million up to July 31, 2013, respectively. If the Plaintiff fails to pay the said amount by the due date, the unpaid amount shall be paid in addition to the damages for delay calculated at 20% per annum from the following day of the due date to the date of payment (Article 1-A).

(A) The land in the Chungcheong-gun C (hereinafter referred to as “instant real estate”) shall be:

(B) remove 39.6 square meters of locking rooms installed above (Article 1-2).

(B) The defendant waives the remainder of the claim.

(2) The costs of lawsuit are assessed against each party.

(3) The plaintiff and the defendant did not object to the decision of recommending the settlement of this case. (2) The plaintiff did not pay the money according to the compulsory auction and the decision of recommending the settlement of this case. (3) The defendant did not pay the money according to the decision of recommending the settlement of this case. (1) A of the decision of recommending the settlement of this case as to the real estate of this case to Cheongju District Court Youngdong Branch D

On November 26, 2014, the compulsory auction had been applied for the money stated in the claim amount, and accordingly the registration of the decision to commence compulsory auction was completed.

2. On May 19, 2015, the Plaintiff 1-A of the Defendant’s decision to recommend the settlement of this case.

Suwon District Court Decision 4738 of 2015 (hereinafter referred to as "two million won and one of them) based on the rate of 20% per annum from July 1, 2013 to May 19, 2015, the deposit date, from July 19, 2015, to May 19, 2015, for delay damages of 376,986 won, and the remaining one million won, with the rate of 20% per annum from August 1, 2013 to May 19, 2015, following the due date for repayment, to KRW 360,000 per annum from August 1, 2013 to May 19, 2015.