beta
(영문) 서울북부지방법원 2017.02.10 2016고단5438

사기

Text

A defendant shall be punished by imprisonment for a term of one year and two months.

Reasons

Punishment of the crime

"2016 Highest 5438"

1. The Defendant, a person who had operated the interior with the trade name of “D” in the Jung-gu Seoul Metropolitan Government shopping district, will be responsible for remodeling construction of apartment at a price less than that of other artificial complex companies, which is lower than that of other artificial complex companies.

The following facts are that it is difficult for the victims to normally perform construction even if the existing obligation is excessive and the construction cost is received from the victims, but around December 27, 2015, the victim E will work at a price lower than that of other subjects.

In the event that a large amount of down payment is paid, it is false that the construction work is completed within the construction period, and if the remainder of the construction is paid, it is a list of crimes attached to the attached Table 4 pages of the judgment by August 27, 2016, including the acquisition by receiving KRW 2.5 million from the injured person as the construction cost in the form of the construction cost.

As described in the statement, it received 9,9510,000 won in total as construction cost from nine victims.

"2016 Highest 5632"

2. The Defendant, as a person who had operated the interior with the trade name “D” in the Jung-gu Seoul Metropolitan Government shopping mall, will have the apartment remodeling construction work at the price of the apartment at a lower price than that of other artificial complex companies against those who have moved to the said apartment.

The following facts are that it is difficult for the victims to normally perform construction even if the existing obligation is excessive and the construction cost is received from the victims, but around April 4, 2015, the above apartment commercial building office will be made at the victim F at a price lower than that of other subjects.

If a large sum of down payment is made, the construction work shall be completed within the construction period, and if all the balance of the construction work is paid, the attached stuff, etc. shall be service.