(영문) 대구지방법원상주지원 2017.11.15 2017가단2013

건물인도 등

Text

1. The defendant delivers the building indicated in the attached list to the plaintiff, and the above building from August 20, 2017 to the plaintiff.

Reasons

1. On July 27, 2016, the Plaintiff indicated and leased a building indicated in the attached list to the Defendant as KRW 5 million, the period from August 19, 2016 to August 19, 2018, and the rent amounting to KRW 350,000 per month.

The Plaintiff does not pay the rent from September 19, 2016 to the Plaintiff and thus terminate the said lease contract.

Accordingly, the plaintiff reached the claim of this case.

2. Article 208 (3) 1 of the Civil Procedure Act of the applicable provisions of Acts.