(영문) 창원지방법원진주지원 2019.12.10 2018가단33851

손해배상(산)

Text

1. The Defendant’s KRW 161,729,744 for the Plaintiff and 5% per annum from November 26, 2016 to December 10, 2019.

Reasons

1. Basic facts

A. The pertinent Plaintiff (CB) is the employee of the LABD (hereinafter “Nonindicted Company”) and the Defendant is the insurer who entered into a contract with Nonparty Company for employee accident compensation insurance (hereinafter “instant insurance contract”).

B. (1) In the event of an industrial accident, the Plaintiff, according to the direction of the non-party company from November 24, 2016, posted electric wires at the electrical room in Sacheon-si E’s second place of business, along with G at the site manager at the A.M., and in P.M., in G from the first floor above the ground to the first floor above the ground.

(2) At around 14:00 on November 26, 2016, the Plaintiff was engaged in the process of connecting the entire distribution by drawing electric wires in the above electrical room, and was just used as the wind to contact other electric wires passing through the 6,600 volts.

(3) As a result, the Plaintiff suffered injury, such as electric images (3.4 degrees), cerebral spawn, spawn 2 spawn, upper boxes open to the right side, electric images (3.4 degrees) on the left side, electric images (3.4 degrees) on the right side and sub-chapters on the water side and sub-chapters on the water side (3.4 degrees), pressure frame for spawn, 1,5 spawnitiss on the right side

(hereinafter “instant industrial accident”) C.

(1) The Plaintiff, immediately after the same day, was sent to the Gyeong-si Hospital located in Jinju, transferred to the H hospital, and was discharged on June 23, 2017.

(2) After that, the Plaintiff continued medical treatment by means of two copies, drums, hys, and hysia, etc. until November 23, 2017.

(3) Meanwhile, the Plaintiff received temporary disability compensation benefits from the Korea Workers’ Compensation and Welfare Service (hereinafter “Korea Workers’ Compensation and Welfare Service”) from November 26, 2016 to November 23, 2017, and (2) receives disability benefits as pension (hereinafter “the lump-sum conversion amount”).

[Ground for Recognition: Facts without dispute, entry of Gap evidence 1 through 18, Eul evidence 1 through 8 (including paper numbers), each physical appraisal result, the whole purport of pleadings]

2. The assertion.