1. The Defendant (Counterclaim Plaintiff) paid KRW 217,691,491 to the Plaintiff (Counterclaim Defendant) and its payment from January 9, 2016 to the date of full payment.
1. Basic facts
A. The Plaintiff is engaged in the business of manufacturing chemical parts, such as chemical parts located in the industrial base, etc., and the Defendant is engaged in the business of manufacturing electronic chemical parts, such as the absorption of electromagnetic waves.
B. From June 2014 to August 2015, the Plaintiff continued to supply the original parts of various industrial materials to the Defendant. The Defendant manufactured the original parts of the Plaintiff’s supply through a variety of processing processes, such as prohibiting selly from sellying on the original parts of the supply, and sold them to the customers.
However, the specific process of the Defendant’s painting on the original surface of the Plaintiff’s supply is carried out in the order of sloping, mountain, preliminary sediment, promotion, activation, primary nitroklym gold, copper gold, secondary nitroklyklym gold, drying, inspection, and pass-up. In most of this process, it is carried out through automated equipment.
C. From June 1, 2015 to August 6, 2015, the Plaintiff supplied a group of KRW 497,691,491 to the Defendant (i.e., KRW 138,97,720 on June 6, 2015; KRW 215,516,686 on July 1, 2015; KRW 143,217,085 on August 1, 2015; and the Defendant paid the remainder of KRW 217,691,491 (= KRW 497,691, KRW 491, KRW 280,000) to the Plaintiff on September 1, 2015.
Meanwhile, the Defendant was partially returned its original parts on the ground that there was a defect in the subject Esti Co., Ltd. (hereinafter “subject Esti”) from June 15, 2015 to August 11, 2015, and in FN370 to August 7, 2015, the FN370 parts sold from June 12, 2015 and DP370 parts, and was returned from Mesti Co., Ltd. (hereinafter “Mesa”), which is the business partner, from September 22, 2015, and from 25 FFC parts sold on September 21, 2015.
E. On October 6, 2015, which was after the filing of the instant lawsuit, the Defendant paid 200 million won out of the original amount to the Plaintiff on October 6, 2015, and paid 130 million won out of the remainder of the original amount until December 31, 2015, and paid the remainder of 80 million won from March 2016 to April 2016.