beta
(영문) 서울중앙지방법원 2017.12.20 2016가합528224

공사대금

Text

1. The Defendant’s KRW 221,863,80 to the Plaintiffs and 6% per annum from July 4, 2016 to December 20, 2017.

Reasons

1. Around March 2015, the facts of recognition were each contracted by the Defendant for the Construction of Housing Site Development Project (hereinafter “Housing Site Development Project”) on the ground B in Echeon-si for the construction of a electric power resource complex, and around April of the same year, the construction of the said housing site and BOX construction (hereinafter “the Housing Site Development Project,” and the construction of the instant construction, including BOX construction and construction of build block and BOX construction.”

The main contents of the instant construction contract are as follows.

B Housing Site Development Corporation

1. Person placing an order: the ballast learning Co., Ltd.;

2. The name of subcontracted construction: The Housing Site Development Corporation at Echeon-si.

3. Construction site: Gyeonggi-do Leecheon-si B;

4. Period of construction: Contract price on March 2015, and September 5, 2015, as of September 5, 2015: KRW 584,00,000 (Additional dues).

7. Items and quantities of materials to be paid: The parties to a separate attachment of the calculation statement shall conclude this construction subcontract in accordance with the terms and conditions of the subcontract for the annexed construction project, the design drawing one, and the specifications, and prepare two copies of the contract, respectively.

Construction Do block and BOX Construction

1. Person placing an order: the ballast learning Co., Ltd.;

2. Subcontract work name: Construction block and BOX work.

3. Construction site: Gyeonggi-do Leecheon-si B;

4. Period of construction: Commencement on April 4, 2015, and completion on September 5, 2015: 106,000,000 won (excluding surtax).

7. Items and quantities of materials to be paid: The parties to the separate attachment of the calculation statement shall have two copies of the contract under this construction subcontract agreement entered into in accordance with the terms and conditions of the attached construction subcontract, design drawings, and specifications, respectively.

The Plaintiffs commenced the instant construction work around March 2015.

After that, on February 2, 2016, Plaintiff A sent to the Defendant a certificate of content that the Defendant would pay the unpaid construction cost for the instant construction work.

After that, the defendant, which was prepared by the plaintiffs as of February 23, 2016, is on the construction completion certificate (from March 6, 2015 to September 6, 2015).