(영문) 서울남부지방법원 2017.07.06 2015가합4857

추가공사대금

Text

1. The Defendant (Counterclaim Plaintiff) shall:

A. On April 23, 2016, Plaintiff (Counterclaim Defendant) KRW 69,612,741 and KRW 55,397,796 among them

Reasons

A principal lawsuit and counterclaim shall also be deemed a principal lawsuit and counterclaim.

Basic Facts

A. The Plaintiff is a stock company engaged in building work business, engineering work business, etc., with the trade name of “building work”, and the Defendant is a private businessman who engages in gas station and lease business with the trade name of “B.”

B. Around September 2014, the Defendant decided to purchase the instant land with D Co., Ltd. (hereinafter “Co., Ltd.” in the name of the company omitted), but D Co., Ltd. (hereinafter “Co., Ltd.”) becomes the co-ownership right for D’s share ratio in January 1/6647.2. The Defendant becomes the co-ownership right for the share ratio in January 1/66472, 1984, and D is the owner of the share right for D’s share on the above land (hereinafter “instant maintenance station, etc.”), and the Defendant decided to newly construct the automobile maintenance station and inspection station (hereinafter “instant gas station”), and the gas station (hereinafter “instant gas station”).

C. Around September 19, 2014, the Defendant: (a) requested the design drawing of the instant gas station to the E architect office (hereinafter “E Architectural Office”); and (b) entered into a construction contract with the Plaintiff to newly construct the instant gas station (hereinafter “instant construction”) with the equipment to be in charge; and (c) concluded a construction contract with the Plaintiff to newly construct the gas station at KRW 1,430,000,000 for the construction cost of the instant gas station (hereinafter “the instant construction contract”); and (d) the main contents are as follows.

3. Date of commencement: The date scheduled for completion on October 14, 2014: The contract amount on April 12, 2015: 1,430,000 won (including value-added tax): The rate of delayed payment: 0.1%: the contractor and the contractor promise to conclude the contract in accordance with the agreement and faithfully perform their contractual obligations in good faith, and prepare two copies of the contract documents as evidence of this contract and keep one copy of each contract document.

Attachment documents: 1.1.