beta
(영문) 서울동부지방법원 2016.09.09 2016가단9255

물품대금 등

Text

1. As to the Plaintiff KRW 35,719,676 and KRW 10,00,00 among them, the Defendant shall pay the Plaintiff KRW 35,719,676 from May 27, 2006, and KRW 25,719,676.

Reasons

1. A cited part;

(a) Indication of claims: To be as shown in the reasons for the claims;

(b) Judgment by publication (Article 208 (3) 3 of the Civil Procedure Act)

2. On October 1, 2015, the rate of damages for delay exceeding 15% per annum is changed from October 1, 2015 to 15% per annum from the day after the day when the complaint of this case was served on the defendant with respect to KRW 35,719,676 of the Plaintiff’s claim to dismiss the part, and thus, the damages for delay exceeding 15% per annum is dismissed.