(영문) 서울중앙지방법원 2019.06.10 2019가단5019729

구상금

Text

1. The Defendants jointly committed against the Plaintiff KRW 77,419,260, and against the Defendant B from January 26, 2016. < Amended by Act No. 15095, Jan. 26, 2019>

Reasons

1. The description of the grounds for the claim shall be as specified in the attached Form;

2. Judgment without holding any pleadings (Articles 208 (3) 1 and 257 (1) of the Civil Procedure Act);

3. As the provisions pertaining to statutory interest rates under the main sentence of Article 3(1) of the Act on Special Cases concerning the Promotion, etc. of Partial Dismissal Lawsuit were promulgated on May 21, 2019 and enforced on June 1, 2019, only the portion of damages for delay calculated at the rate of 15% per annum from the day following the delivery of a copy of the complaint of this case until May 31, 2019, and 12% per annum from the next day to the day of complete payment, shall be cited, and the portion in excess shall be dismissed.