beta
(영문) 청주지방법원충주지원 2015.12.24 2015가합472

물품대금

Text

1. The Defendant: (a) KRW 380,195,58; and (b) annually from September 16, 2014 to November 11, 2015 to the Plaintiff.

Reasons

1. Items claim amounting to KRW 380,195,588, which occurred from around 2006 to September 15, 2014 by the Plaintiff’s marking of the claim from around 2006 to around 200, 380,195,58

2. Articles 208 (3) 3 and 194 of the Civil Procedure Act of the applicable provisions of Acts;

3. Some dismissed parts claim damages for delay at the rate of 20% per annum from the day after the original copy of payment order was served to the day of complete payment. However, as the provisions on statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings were amended by Presidential Decree No. 26553 on September 25, 2015, the interest rate for delay damages under the same Act was changed from 20% per annum to 15% per annum from October 1, 2015 to 20% per annum, the part