beta
(영문) 수원지방법원 2015.08.20 2015가단553

용역비

Text

1. The defendant shall pay to the plaintiffs the amount of KRW 25,00,000 and each of the above amounts from December 4, 2014 to the day of full payment.

Reasons

The Plaintiffs were commissioned to provide design services for the construction of a factory by developing Pyeongtaek-si and three lots owned by the Defendant (hereinafter “instant real estate”). The Defendant paid KRW 2,00,000,000 to the Plaintiff Co., Ltd. on April 9, 2013, and KRW 30,000 on July 30, 2013, respectively. On October 4, 2013, if the Plaintiffs and the Defendant represented on October 4, 2013, the survey and design services contract (hereinafter “instant contract”) including construction costs of KRW 5,00,00,000, and the remainder other than the start payment of KRW 50,000,000,000,000 from the date of obtaining approval for the new construction of a factory for the instant real estate, or the Defendant paid KRW 3,00,000 to the representative director of the Plaintiff on July 30, 2014 to the Defendant’s witness testimony each of the instant real estate.

Therefore, the defendant is obligated to pay to the plaintiffs damages for delay calculated at the rate of 20% per annum under the Act on Special Cases concerning the Promotion, etc. of Legal Proceedings from December 4, 2014 to the day of full payment, as requested by the plaintiffs, with respect to each of the above amounts of 25,00,000 won and each of the above amounts under the contract of this case.

Therefore, the plaintiffs' claim of this case is justified and it is so decided as per Disposition by the assent of all.