공사대금
1. Upon receipt of a claim changed in exchange at the trial, the Defendant shall pay to the Plaintiff KRW 28,100,000 and KRW 30,625 to the Plaintiff B.
1. Basic facts
A. On March 7, 2015, F was awarded a contract by the Defendant for a new construction project on the G-based G-based G-based G-based G-based G-based G-based G-based G-based G-based G-based G-based (hereinafter “instant construction project”) with the construction cost of KRW 330,000,000 and the construction period from April 10, 2015 to June 20, 2015.
B) Around May 27, 2015, Plaintiff A received KRW 38,100,000 for the construction cost of the instant subcontracted project; the construction cost of KRW 15,000 for the instant subcontracted project; and the settlement of the remainder within 20 days after the 3th floor cryp dismantling is completed; and pursuant to the said subcontract, the said wooden project was completed on August 10, 2015; and the Defendant paid KRW 10,000,000 for the said subcontracted project directly to Plaintiff A around July 9, 2015.
C. (1) Around August 18, 2015, Plaintiff B had the construction cost of KRW 42,689,000, and the construction cost of the instant construction work was paid in advance before the construction. (2) Plaintiff B commenced the construction work in accordance with the said subcontract, and Plaintiff B suspended the construction work on October 10, 2015, even if the F did not pay the construction cost agreed to pay in advance.
Around that time, F and Plaintiff B agreed to settle the work cost at KRW 35,525,600 at the time of the discontinuance of the work.
3) Meanwhile, around October 10, 2015, the Defendant directly paid Plaintiff B KRW 4,90,000, which is a part of the above settlement agreement amount. D. 1) Plaintiff C was subcontracted from F around September 1, 2015, and from September 20, 2015 to October 30, 2015, the construction period of interior works among the instant construction works shall be KRW 146,30,00 for the construction cost, and the contract payment shall be KRW 43,890,00 for the intermediate payment, KRW 58,520,00 for the intermediate payment, and KRW 43,890,00 for the remainder payment.
2. After October 26, 2015, Plaintiff C commenced construction works from October 26, 2015 due to the delay in the preceding process, and Plaintiff C did not pay the construction cost agreed to be paid in advance by F. The construction works around November 7, 2015.