공사대금
1. The Defendant shall pay to the Plaintiff KRW 495,00,000 and the interest rate of KRW 15% per annum from August 26, 2017 to the date of full payment.
1. Indication of claim;
A. On April 2012, the Plaintiff was entering into a subcontract with the Defendant for the construction work of windows, glass, etc. among the construction work of the construction work of the construction work of the construction work of the construction work of the building of the building of the building of the building of the building of the building of the building of the building of the building of the building of the building of the building of the building of the building of the building of the building of the building
(90%) b) fair rate of 90%)
On October 16, 2017, the Defendant promised to pay the Plaintiff KRW 495,00,000 as the construction cost of the subcontracted project in this case.
C. Therefore, the Defendant is liable to pay the Plaintiff the construction cost of KRW 495,00,000 and the damages for delay calculated at the rate of 15% per annum from the day after the original copy of the instant payment order was served to the day of complete payment.
2. Articles 208 (3) 2 and 150 (3) of the Civil Procedure Act of the applicable provisions of Acts;