물품대금
1. The Defendant shall pay to the Plaintiff KRW 38,760,000 and the interest rate of KRW 15% per annum from August 30, 2017 to the day of complete payment.
On July 7, 2015, the Plaintiff entered into a contract with the Defendant to supply price of KRW 9,6760,000 (including value-added tax; hereinafter the same shall apply) for the main household and the main household to be installed in the apartment house located in Daegu-gun District A (hereinafter referred to as “instant contract”); according to the instant contract, the Plaintiff supplied the said main household and the main office to the Defendant from August 5, 2015 to December 12 of the same month; and the Defendant paid KRW 58 million to the Plaintiff on July 15, 2015 as the price for the goods, either there is no dispute between the parties, or may be recognized by comprehensively taking into account the overall purport of arguments as set forth in subparagraphs 1 through 3.
According to the above facts, the defendant is obligated to pay to the plaintiff 3,8760,00 won for the remaining goods (=96.76 million won - 58 million won) and damages for delay calculated at the rate of 15% per annum from August 30, 2017 to the day of full payment, which is the day following the delivery of a copy of the complaint of this case.
Therefore, the plaintiff's claim of this case is legitimate, and it is decided as per Disposition by admitting it.