beta
(영문) 수원지방법원안양지원 2016.03.09 2015가단109667

건물명도

Text

1. The defendant shall be the plaintiff.

A. Of the real estate listed in the separate sheet, (i) the indication of the separate sheet (i), Doz, Myeonz, Myeonz, and (ii) the separate sheet.

Reasons

1. The description of the grounds for the claim shall be as specified in the attached Form;

2. Article 208 (3) 1 of the Civil Procedure Act.

3. Some dismissal parts of the “Rules on the statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases concerning Expedition, etc. of Legal Proceedings” were amended, and the legal interest rate for a case for which the first instance trial has not been concluded until October 1, 2015, the Plaintiff applied the interest rate of 20% per annum under the previous provisions until September 30, 2015, and the interest rate of 15% per annum under the amended provisions from October 1, 2015, respectively.

1.(b)

The damages for delay calculated at the rate of 20% per annum from December 6, 2015 to the day of full payment, which is the day following the delivery of a copy of the complaint in this case, exceeds the damages for delay calculated at the rate of 15% per annum, shall be dismissed.