(영문) 수원지방법원 2017.04.25 2016가단45249

공사대금

Text

1. The defendant shall pay 24,350,000 won to the plaintiff and 15% per annum from September 28, 2016 to the day of complete payment.

Reasons

The Plaintiff agreed to construct the portion of the metal construction work among the new construction works of the officetel located in Osan City with the Defendant at KRW 50,000,000, and completed the construction work. The Defendant did not pay KRW 24,350,000 up to the date of the construction work payment, the fact that the Defendant did not pay KRW 24,350,000 pursuant to the purport of the evidence

The Plaintiff asserted the remainder of the first construction cost as KRW 43,050,000, but the Defendant asserted that it was KRW 24,350,000, and finally reduced or changed the claim amount in conformity with the Defendant’s assertion.

Therefore, the defendant is obligated to pay to the plaintiff 24,350,000 won and the damages for delay calculated at the rate of 15% per annum from September 28, 2016 to the date of full payment following the delivery of the application for the payment order of this case. Thus, the defendant is obligated to pay to the plaintiff 24,350,000 won per annum under the Act on Special Cases Concerning the