1. The defendant's appeal is dismissed.

2. The costs of appeal shall be borne by the Defendant.

Purport of claim and appeal

1..

Reasons

1. Basic facts

A. On November 201, 2013, the Plaintiff was requested by the Defendant to estimate the design of lighting fixtures in Eunpyeong-gu Seoul (hereinafter “instant building”) with the trade name of “C” and the exterior lighting design of the building.

B. On November 27, 2013, the Defendant deposited KRW 5,280,00 in the design deposit for lighting of the instant building to the Plaintiff. On December 2, 2013, the Plaintiff provided the Defendant with the design drawing for lighting the columns and the part-to-date floor mino of the instant building at the Defendant’s request.

C. On December 11, 2013, the Plaintiff and the Defendant agreed to substitute KRW 5,280,000 as the down payment of KRW 5,40,000 for the instant contract deposit, and the Defendant confirmed that the Plaintiff submitted the construction design documents from the Plaintiff (hereinafter “instant contract”). The Plaintiff agreed to substitute KRW 5,280,000 as the down payment of KRW 5,40,000 for the instant contract, and the Defendant was submitted the construction design documents from the Plaintiff (hereinafter “instant contract”).

The details of the instant contract are as follows.

1) The first installment payment method: 5,400,000 won intermediate payment of KRW 5,000: the second installment payment of KRW 5,00,000 (at the time of the completion of construction of the LED bricks: 5,000,000 (at the time of the completion of construction of the part part of the wall): The remainder of KRW 7,600,000 (within 3 days after the completion of construction of the front part of the wall): the provision of construction drawings and specifications based on construction: until December 12, 203: 16:0 of the front part of the columns of KRW 102 until December 14, 2013; the defendant shall not be liable for the termination of the contract at any time until December 16, 2013; the defendant shall be liable for the termination of the contract at any time and at any time until December 30, 2013; the defendant shall be liable for the termination of the contract at any time;